Work Progress #3

Clients Hutchison Ports ICAVE attended a cocktail party where the status of the New Port of Veracruz was informed.
The work of the new Terminal ICAVE continues to evolve favorably, planning that the major equipment will grow 40% in the first phase, with 7 container ship cranes in the dock, including two recently acquired. It will be May 2019 the date on which Hutchison Ports will be prepared to receive the first vessel in its dock of 700 linear meters corresponding to the first phase, doubling our current capacity once the second phase of ICAVE is completed with 1,050 m.
This transformation is the result of market confidence in the port of Veracruz, as well as the excellent management of a highly experienced port community, as it is the most efficient port in the Gulf of Mexico and, with this investment, will raise its operations to a higher level.
SusanaDiaz-FranciscoOrozco

Lic. Susana Diaz Virgen, General Manager, Hutchison Ports ICAVE. Lic. Francisco Orozco Mendoza, Commercial Director, Hutchison Ports Mexico

On Thursday, August 2nd, we had the pleasure of living with our clients in Mexico City, through a cocktail event that took place at Hacienda Los Morales, a site where a film was shown that illustrated the progress of the magna work of the new port of Veracruz that reaches today a 44% advance, as well as the sample of a migration process of 7 months that guarantees the simultaneous uninterrupted operation in both terminals until November 2019, maintaining service levels and attention according to our philosophy, oriented to the client.

Finally, and clearly, a message was delivered by our Commercial Director and our General Manager, about what Veracruz offers and what maintains it as a port reference, without problems of congestion, or schedule restrictions. Complementing in addition with technological innovation and strategic infrastructure as part of the strengths that consolidate the recognized advantages offered by the port of Veracruz.

ReportedeAvancedeObra3-3

Hutchison Ports ICAVE customers setting their names as a symbol of belonging to the new era.

Progress of the work of the new port of Veracruz

The advances that are carried out in the construction of the ICAVE terminal in the New Port of Veracruz are the following:

  • The hopper and cutter dredges finished their activities in this project, leaving the docks and navigation areas dredged to a depth of 15 m.
  • The works of the dock continue advancing in the superstructure, which is at 45% of construction.
  • In yard progress is made in soil improvement through dynamic compaction, vibroflotation and overburden, with an advance of 35%; The introduction of drainage lines has a 13% advance.
Hutchison Ports is the port and related services division of CK Hutchison Holdings Limited (CK Hutchison). Hutchison Ports is the world’s leading port investor, developer and operator with a network of port operations in 52 ports spanning 26 countries throughout Asia, the Middle East, Africa, Europe, the Americas and Australasia.